#WEEK 29 [MAY 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)

 Summary of Week 29 works:

  • Gabion Wall 90% complete
  • Triangulated pocket garden – Low retaining wall complete!
  • Triangulated pocket garden – New RC Footpath 60% complete
  • Expansion of Works - New/Upgraded RC footpath and drain in front of the houses are ~70% completed
  • Expansion of Works – Slope Reshaping works in progress
  • Expansion of Works - Cascading drain and new staircase to connect footpath to Renovated Toilet at Traffic Garden in progress.
As its MCO (Movement Control Order) again, we could not physically visit the site and are working from home. However, we could surprisingly good range with our DJI Mini 2, so here's a progress update video instead!




Comments