#WEEK 37 [JULY 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
** Due to the 6 weeks of Movement Control Order (MCO) aka Lockdown due to Covid 19 between 29.05.2021 (Week 30) till 14.07.20221 (Week 36); there hasn’t been any updates.**
Summary of Week 37 works
- Triangulated pocket garden – nearing completion
- Planting Beds – in progress
- Rectification Work at End Chainage - Complete
- Connecting interface between triangulated pocket garden and gravel footpath pt2 / gabion wall area – in progress
- Gabion Wall – Complete
- Rectification work at truncation to existing drain at junction interface with main drain – in progress
- Turfing works at green open spaces along gravel footpath pt1 – in progress
- Expansion of works & slope reshaping works – almost complete