#WEEK 43 [SEPT 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
Summary of Week 43 works:
- Connecting Pavilion – Installation of seating benches in progress
- Entrance Pavilion – Installation of Low-E glass roof complete
- Entrance Pavilion – Installation of capping for grating joints in progress
- Entrance Pavilion – Installation of handrails in progress
- Entrance Pavilion – Installation of all anticlimb fencing complete
- Electrical Works – All compound lighting poles installation complete
- Crossover 2 – Installation of handrail at crossover entrance and exit complete
- Expansion of Works – All side access footpath complete
- Gravel Footpath pt1 – Preparation of topsoil for turfing at open space in progress
- Triangulated Pocket Garden – Entrance to pocket garden constructed
- MBKS in-house Landscaping works in progress