#WEEK 43 [SEPT 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)

 

Summary of Week 43 works:

  • Connecting Pavilion – Installation of seating benches in progress
  • Entrance Pavilion – Installation of Low-E glass roof complete
  • Entrance Pavilion – Installation of capping for grating joints in progress
  • Entrance Pavilion – Installation of handrails in progress
  • Entrance Pavilion – Installation of all anticlimb fencing complete
  • Electrical Works – All compound lighting poles installation complete
  • Crossover 2 – Installation of handrail at crossover entrance and exit complete
  • Expansion of Works – All side access footpath complete
  • Gravel Footpath pt1 – Preparation of topsoil for turfing at open space in progress
  • Triangulated Pocket Garden – Entrance to pocket garden constructed
  • MBKS in-house Landscaping works in progress