Summary of Week 4 works:

  • Project Launching by MBKS Mayor (Dato Wee Hong Seng) and Minister of Local Government and Housing Sarawak (Dato Sri Dr. Sim Kui Hian)
  • Continuation of Footpath Upgrading works
  • Continuation of New Gravel Footpath setting out
  • Continuation of New Entrance Pavilion setting out
  • Continuation of New Connecting Pavilion setting out
  • Preparation of moulds and production area for pre-cast RC drain covers
  • Setting up project banner outside of the Site Office at the existing Caretaker’s Quarters (located inside Traffic Garden)




Real-time progress of 4 weeks’ worth of site work.