#WEEK 6 [DEC 2020]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
Summary of Week 6 works:
- Continuation of Footpath Upgrading works
- Continuation of New Gravel Footpath works
- Adjusting level of New Entrance Pavilion to suit site conditions
- On site adjustments to suit site conditions
- Crossover 1 & 2 piling and preparation of formwork
- Test Pile and PDA at New Entrance & Connecting Pavilion