#WEEK 12 [JAN 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
Summary of Week 12 works:
- Preparation of formwork for New Entrance Pavilion footing
- Continuation of New Connecting Pavilion works
- Continuation of Crossover 1 & 2 construction works
- Continuation of Footpath Upgrading works
- Continuation of New Gravel Footpath works