#WEEK 20 [MARCH 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)

 

Summary of Week 20 works:

  • Site Visit by Minister MBKS Mayor
  • Completion of footings and retaining wall for Entrance Pavilion Phase 2
  • Gravel footpath Part 1 turfing and slope reshaping (continued)
  • Gravel footpath Part 2 filling, and construction of RC drains (continued)