#WEEK 17 [MARCH 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)

 

Summary of Week 17 works:

  • Connecting Pavilion (aka Kenyalang Rainbow Bridge) painting
  • Entrance Pavilion footings and retaining wall complete to current stage
  • Completion of Crossover 2 casting
  • Discussion and on site setting out / marking of pole lighting
  • Continuation of slope shaping and earthworks