#WEEK 25 [APRIL 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
- Entrance Pavilion – Painting (in progress)
- Entrance Pavilion – Ramp/Stair connection to Gravel Footpath Pt1
- Footpath upgrading works between Footpath 1 & 2
- Gravel Footpath Pt1 – Construction of footings for lighting poles
- Gravel Footpath Pt2 – Installation of 32m Gabion Wall (in progress)
***