Summary of Week 25 works:

  • Entrance Pavilion – Painting (in progress)
  • Entrance Pavilion – Ramp/Stair connection to Gravel Footpath Pt1  
  • Footpath upgrading works between Footpath 1 & 2
  • Gravel Footpath Pt1 – Construction of footings for lighting poles
  • Gravel Footpath Pt2 – Installation of 32m Gabion Wall (in progress)





***

Overall site progress for April 2021