#WEEK 28 [MAY 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)

 


Summary of Week 28 works:

  • Relocation of 2 nos of Telekom Pole at front and back of Entrance Pavilion
  • Gabion Wall almost complete
  • Residents starting to plant in community planter beds
  • Triangulated pocket garden – Low retaining wall almost complete
  • Triangulated pocket garden – New RC Footpath under construction
  • Expansion of Works - New/Upgraded RC footpath and drain in front of the houses are ~70% completed
  • Expansion of Works – Slope Reshaping works in progress
  • Expansion of Works - Cascading drain and new staircase to connect footpath to Renovated Toilet at Traffic Garden in progress.