#WEEK 28 [MAY 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
Summary of Week 28 works:
- Relocation of 2 nos of Telekom Pole at front and back of Entrance Pavilion
- Gabion Wall almost complete
- Residents starting to plant in community planter beds
- Triangulated pocket garden – Low retaining wall almost complete
- Triangulated pocket garden – New RC Footpath under construction
- Expansion of Works - New/Upgraded RC footpath and drain in front of the houses are ~70% completed
- Expansion of Works – Slope Reshaping works in progress
- Expansion of Works - Cascading drain and new staircase to connect footpath to Renovated Toilet at Traffic Garden in progress.