#WEEK 27 [MAY 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
Summary of Week 27 works:
- Expansion of Works in progress.
- Gabion wall in progress
- RC footpath 7 adjacent to Entrance Pavilion partially complete
- Upgrading of side lanes and triangulated pocket garden under construction
- Works at Triangulated Pocket Garden started
- Replacement benches at Toilet Shed (in traffic garden) installed!