#WEEK 40 [AUG 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)


Summary of Week 40 works

  • Crossover 1 & 2 – Installation of integrated handrail seating in progress
  • Crossover 3 – RC Ramp to existing traffic garden complete
  • Crossover 3 - Formwork in progress
  • Connecting Pavilion – Installation of floor grating complete
  • Connecting Pavilion – Installation of capping for anticlimb fencing in progress
  • Entrance Pavilion – Belian piling for new RC ramp connection complete, casting of rc ramps in progress
  • Entrance Pavilion – Installation of capping for anticlimb fencing in progress
  • Gravel Footpath pt2 (Gabion Wall Area) – J Drain complete
  • Gravel Footpath pt2 - Gravel base in progress
  • Gravel Footpath pt1 - Turfing along gravel footpath shoulder (adjacent to main drain) in progress
  • Gravel Footpath pt1 – Rock embankment along main drain between crossover 1 and 2 in progress
  • Electrical Works - Electrical pillar and lighting pole along gravel footpath pt1 complete
  • Planter Bed – Some residents have started their planting
  • Triangulated pocket garden – Turfing in progress