#WEEK 40 [AUG 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
Summary of Week 40 works
- Crossover 1 & 2 – Installation of integrated handrail seating in progress
- Crossover 3 – RC Ramp to existing traffic garden complete
- Crossover 3 - Formwork in progress
- Connecting Pavilion – Installation of floor grating complete
- Connecting Pavilion – Installation of capping for anticlimb fencing in progress
- Entrance Pavilion – Belian piling for new RC ramp connection complete, casting of rc ramps in progress
- Entrance Pavilion – Installation of capping for anticlimb fencing in progress
- Gravel Footpath pt2 (Gabion Wall Area) – J Drain complete
- Gravel Footpath pt2 - Gravel base in progress
- Gravel Footpath pt1 - Turfing along gravel footpath shoulder (adjacent to main drain) in progress
- Gravel Footpath pt1 – Rock embankment along main drain between crossover 1 and 2 in progress
- Electrical Works - Electrical pillar and lighting pole along gravel footpath pt1 complete
- Planter Bed – Some residents have started their planting
- Triangulated pocket garden – Turfing in progress
Comments
Post a Comment