#WEEK 41 [AUG 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)


Summary of Week 41 works

  • Crossover 1 & 2 – Installation light fittings in progress
  • Crossover 3 – Complete!
  • Connecting Pavilion – Installation of light fittings in progress
  • Entrance Pavilion – Casting of access footpath and ramps in progress
  • Entrance Pavilion – Installation of floor grating in progress
  • Entrance Pavilion – Installation of glass roof in progress
  • Entrance Pavilion – RC verge at entrance pavilion apron complete
  • Gravel Footpath pt1 – Construction of new RC drain for gravel footpath pt 1 (between crossover 1 & 2) in progress.
  • Gravel Footpath pt2 - Gravel base complete