#WEEK 41 [AUG 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
Summary of Week 41 works
- Crossover 1 & 2 – Installation light fittings in
progress
- Crossover 3 – Complete!
- Connecting Pavilion – Installation of light fittings
in progress
- Entrance Pavilion – Casting of access footpath and ramps
in progress
- Entrance Pavilion – Installation of floor grating in
progress
- Entrance Pavilion – Installation of glass roof in
progress
- Entrance Pavilion – RC verge at entrance pavilion
apron complete
- Gravel Footpath pt1 – Construction of new RC drain for
gravel footpath pt 1 (between crossover 1 & 2) in progress.
- Gravel Footpath pt2 - Gravel base complete