#WEEK 42 [AUG 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)
Summary of Week 42 works
- Entrance Pavilion – Installation of Low-E glass roof in progress
- Entrance Pavilion – Installation of grating for internal ramp in progress
- Entrance Pavilion – Installation of grating for side access ramp in progress
- Entrance Pavilion – Access footpath and ramps to Entrance Pavilion complete
- Plumbing Works – All standpipes installation complete
- Electrical Works – All compound lighting poles installation complete
- Crossover 1 & 2 – Installation integrated handrail seating and light fittings complete
- Crossover 3 – Installation integrated handrail seating complete
- Rock Embankment between Crossover 1 & 2 - Complete
- Gravel Footpath pt1 – Construction gravel footpath pt 1 connection (between crossover 1 & 2) complete
- Gabion Wall – Formwork for RC capping in progress
- Gravel Footpath pt2 – Complete
- MBKS in-house Landscaping works in progress
**********
***********