#WEEK 42 [AUG 2021]: KENYALANG PARK URBAN REGENERATION (Phase 1 – Package 1)


Summary of Week 42 works

  • Entrance Pavilion – Installation of Low-E glass roof in progress
  • Entrance Pavilion – Installation of grating for internal ramp in progress
  • Entrance Pavilion – Installation of grating for side access ramp in progress
  • Entrance Pavilion – Access footpath and ramps to Entrance Pavilion complete
  • Plumbing Works – All standpipes installation complete
  • Electrical Works – All compound lighting poles installation complete
  • Crossover 1 & 2 – Installation integrated handrail seating and light fittings complete
  • Crossover 3 – Installation integrated handrail seating complete
  • Rock Embankment between Crossover 1 & 2 - Complete
  • Gravel Footpath pt1 – Construction gravel footpath pt 1 connection (between crossover 1 & 2) complete
  • Gabion Wall – Formwork for RC capping in progress
  • Gravel Footpath pt2 – Complete
  • MBKS in-house Landscaping works in progress












**********


Summary of Progress up till week 42 (August 2021)

***********